Summary

City staff outlined a plan to develop a domestic‑violence shelter using HOME‑ARP, a federal community project award and general‑fund dollars; two experienced shelter operators responded to the RFI but raised concerns about residency restrictions, funding for the first two years of operations, and location disclosure.

Irving — City housing staff and consultants briefed the Irving City Council on March 26 on plans to develop a domestic‑violence (DV) shelter funded with HOME‑ARP dollars and additional city and federal funds, and to select an operator through a competitive procurement.

Despec of the city’s housing and redevelopment team and consultants from Grow America and Social Impact Architects said the city has identified multiple funding sources to advance design and construction, including $2 million of HOME‑ARP funds, an approximately $5.8 million congressional community project award and $15 million of proposed general‑fund allocations — a combined funding pool that staff said currently totals about $22.8 million. Staff described a parallel, phased approach: an RFQ for architecture and cost estimation, an RFP for a qualified shelter operator, and a phase‑one due‑diligence period that would produce a go/no‑go recommendation.

Consultants reported two experienced shelter operators responded to the city’s request for information: Archway (operating shelters in Tarrant County) and Mosaic Family Services (operating in Dallas). Both organizations indicated interest but flagged practical concerns, particularly the challenge of financing and reserves for the first two years of operations before state reimbursements are available.

Council concerns and debate

Council members focused on two recurring issues: whether the city’s HOME‑ARP allocation can be used for a shelter dedicated to domestic‑violence survivors without a HOME plan amendment, and whether the city should require a minimum share of shelter capacity be reserved for Irving residents given the city’s capital investment. "We need to take this $2 million and get it out of this domestic violence shelter and go ahead and put it where it was originally approved," Council member Dennis said, referring to prior HOME‑ARP plan priorities and urging a plan amendment if the council keeps the HOME funds assigned to a DV‑only shelter. Dennis and others also pressed staff on safeguards to ensure that Irving taxpayers’ capital investment benefits local residents.

Staff noted federal HOME‑ARP rules require compliance timelines and a construction/operational deadline: the shelter must be built and operating by September 30, 2030 to meet HOME‑ARP expenditure requirements. Consultants said operators must be involved early in design to ensure the facility meets operational needs, and that the city’s approach envisions the operator responsible for day‑to‑day operations and routine maintenance during a long lease/operating period; staff described a planned compliance period (federal monitoring) of 15 years and noted the city may convey fee title after the compliance period subject to future conditions.

Next steps

Staff proposed a parallel procurement schedule (RFQ for architect/cost estimator and an RFP for an operator), a phase‑one design and funding due‑diligence period, and a go/no‑go decision at the end of phase one. Council discussion showed support for advancing procurement while also asking for clarity on how HOME‑ARP funds are used, how Irving residents’ needs will be prioritized, and how operational reserves for the first two years will be secured. No final decision to obligate construction dollars was made at the work session; staff will bring procurement documents and phase‑one findings back to council for action.