Summary

Bondry Consulting presented the DLGF-format annual TIF report for 2025; commissioners approved submitting the report, were reminded that many TIF districts expire in 2031–32 and will revert increments to overlapping units, and received updates on the training facility, Judicial Center, HCRUD phases and wind-related building damage.

Bondry Consulting consultant Oscar Gutierrez presented the Hamilton County Redevelopment Commission’s April 15, 2025 Department of Local Government Finance (DLGF) annual report at the commission’s March 17 meeting and the commission voted to submit the report to DLGF.

Gutierrez outlined the report’s format and noted it looks backward at 2025 activity, listing each tax-increment financing (TIF) allocation area, the Indiana code under which each was established, and the dates when those TIF areas will expire. He warned that multiple TIFs are set to expire in 2031 and 2032 and that, when they do, the increment will revert to overlapping taxing units rather than remaining with the commission.

The report also includes revenue and expenditure summaries by allocation area, year-end fund balances for 2025, and a section showing legally pledged revenues to outstanding bonds, detailing principal and interest outstanding and amounts paid to date. Gutierrez emphasized that the P&I outstanding figure reflects the total interest to be paid over life of the obligations, which can appear large though it is an aggregate long-term amount.

Commissioners asked procedural and budget-related questions during and after the presentation. After the report vote, the commission discussed a separate budget item and approved the commission’s 2026 management budget subject to an amendment that will identify where a recently approved $100,000 grant to the Hamilton County Regional Utility District should be charged.

Staff then provided project updates: the training facility has encountered soils issues that remain within budget; HCRUD’s phase one and two work is approaching completion; the Judicial Center procurement and G-max delivery paperwork is being finalized; and county facilities experienced wind-related damage, with gusts reported up to roughly 60 mph, several doors damaged and minor roof impacts.

The commission confirmed its next meeting date for June 1, 2026 at 8:30 a.m. and adjourned.