Central High School bond update: asbestos abatement, locker‑room addition and phased work through 2026

Mesa County Valley School District No. 51 Board
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Owners’ representative Mike Adams and district staff presented design‑development milestones for the Central High School bond project, including asbestos abatement in Feder Hall and locker rooms, a southwest athletics addition (weight and wrestling rooms), and a timeline that targets turnover of the first phase by next November and continued construction through 2026.

Mike Adams, the owners’ representative for the 2024 bond program, and district staff provided a detailed update on Central High School bond work.

Adams said design‑development documents are complete and the team is moving into construction documents. District staff warned that Feder Hall (the library area) contains asbestos in floor tile and a janitor’s closet that must be abated over winter break to preserve a tight construction schedule. Additional asbestos abatement is planned in existing locker rooms beginning in March; that work must be finished before certain construction phases can begin.

The presentation showed renderings and floor plans. The first construction phase will focus on the southwest corner — a new weight room, wrestling room addition and replacement locker rooms — with a planned turnover near November in time for the Warrior Classic. Subsequent phases include a two‑story central addition connecting older buildings and new science classrooms on the second floor.

Contracting teams cited local architect BLE and national partner DLR, with FCI Constructors as the general contractor. Board members asked about student and family engagement in design advisory groups; presenters said staff, students and open houses were part of the process. The board was told the abatement and packing work requires staff contract days and pre‑planning so classrooms can be packed and moved during the summer.