Fairgrounds renovation advances; commissioners debate landscaping, paving and use of READY funds
Summary
Project leads reported $3.67M spent on a $4M fairgrounds renovation and, with state "READY" funds and community foundation pledges, the county has roughly $1.1M available to finish remaining work; commissioners discussed deferring landscaping but keeping electrical and paving plans under review for council approval.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
Project leaders updated Decatur County commissioners on April 20 on a multi-phase fairgrounds renovation that began last year with a $4 million budget. The board heard a line-by-line status report on remaining scope, available funds and options for completing the build-out.
The presenter said $3,671,000 has been spent to date, leaving approximately $329,000 on the county’s BOT (local) balance. State READY funds totaled $519,636.89, and the community foundation held roughly $617,630.62 in cash and pledges, giving the project more than $1.1 million to finish remaining items, including $470,000 in electrical upgrades, $200,000 for midway paving and repairs to the horse barn.
Project staff said fundraising has produced about $600,000 in monetary donations and substantial in-kind labor contributions. "When you combine the over 600,000 at the community foundation with the amount of funds that are available from READY, we have over $1.1 million that's available to this project," the presenter said.
Commissioners debated whether to include $18,000 in decorative landscaping and boulders. One commissioner described landscaping as a "luxury" and recommended deferring it to reduce near-term costs; another favored retaining landscaping while noting maintenance needs. On midway paving, commissioners discussed whether to keep the work in the bond-funded contract (Barnes Construction) to manage bonding and insurance or to bid it separately for potential savings; several members favored leaving paving in the bond package to avoid bonding complexities.
Staff said the total project could rise to about $4.3 million with the proposed additions and that they will present recommendations to the county council because the new total would exceed the original $4 million appropriation. Commissioners did not take a final contract-level vote on optional additions at the meeting but authorized staff to move forward with the current fee schedule and to seek council guidance on any work that would push the project above the initial budget.