City outlines Walnut Street water-main replacement, budgets $350,000 to start work
Summary
City staff described plans to replace aging two-inch water mains on Walnut Street, proposing staged work using trenchless bore methods and allocating roughly $350,000 to begin; initial block work is estimated at $75,000–$99,000.
Get email alerts on the Infrastructure Water topic
No spam. Unsubscribe anytime.
Superintendent Thorberg briefed the commission on a targeted water-main replacement project for Walnut Street, identifying an aging two-inch main that serves three blocks near Stever Park and the school property.
Thorberg said the work would use a bore-and-pull technique to avoid long open cuts, replace two-inch lines with a six-inch main where required, and include pressure testing, chlorination and service reconnections. He estimated the first (most complex) block would cost between about $75,000 and $99,000 once materials and service tie-ins are included, and said the city has approximately $350,000 budgeted for water-main replacements.
Thorberg noted the work would be staged, with the initial southern block (15th to 16th) and the tie to a cross-connection as priorities to create a looped main. He said staff would notify residents in advance and coordinate service relocations. Commissioners indicated budgeted funds and staff availability supported beginning the work.
Next steps: staff will proceed with procurement and scheduling, subject to parts availability and winter ground conditions. The commission offered no objection to starting the prioritized block.