City outlines Walnut Street water-main replacement, budgets $350,000 to start work

Goodland City Commission · November 4, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff described plans to replace aging two-inch water mains on Walnut Street, proposing staged work using trenchless bore methods and allocating roughly $350,000 to begin; initial block work is estimated at $75,000–$99,000.

Superintendent Thorberg briefed the commission on a targeted water-main replacement project for Walnut Street, identifying an aging two-inch main that serves three blocks near Stever Park and the school property.

Thorberg said the work would use a bore-and-pull technique to avoid long open cuts, replace two-inch lines with a six-inch main where required, and include pressure testing, chlorination and service reconnections. He estimated the first (most complex) block would cost between about $75,000 and $99,000 once materials and service tie-ins are included, and said the city has approximately $350,000 budgeted for water-main replacements.

Thorberg noted the work would be staged, with the initial southern block (15th to 16th) and the tie to a cross-connection as priorities to create a looped main. He said staff would notify residents in advance and coordinate service relocations. Commissioners indicated budgeted funds and staff availability supported beginning the work.

Next steps: staff will proceed with procurement and scheduling, subject to parts availability and winter ground conditions. The commission offered no objection to starting the prioritized block.