Weld County approves $378,000 design contract for judicial center, awards $7.4 million asphalt supply

Weld County Board of County Commissioners · March 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Weld County Board of County Commissioners approved a $378,000 design contract for the Weld County Judicial Center and awarded a not-to-exceed $7.42 million hot-and-warm asphalt supply contract, along with smaller public-works supply awards, during its March 2 meeting.

The Weld County Board of County Commissioners on March 2 approved a package of procurement awards that included a $378,000 contract for preliminary design work on a new Weld County Judicial Center and a not-to-exceed $7,422,983 contract for asphalt supplies.

Toby Taylor of the county purchasing office told commissioners the judicial center solicitation drew six proposals and a three-firm short list; the board interviewed finalists. "Fentress Studios as the overall best value for this solicitation," Taylor said, and Facilities recommended awarding Fentress Studios $378,000 for conceptual programming, validation and concept drawings, with other fees to be negotiated later.

Public Works recommended the 2026 hot-and-warm asphalt supply award to the lowest qualified bidder, Martin Marietta Materials Inc., for an amount not to exceed $7,422,983. The board moved and approved the award by voice vote. The county also approved a 2026 crack-seal supply contract to Maxwell Products Inc., for a 2026 not-to-exceed amount of $74,240 (price cited as $1,160 per ton).

Commissioners thanked applicants and noted robust interest in the justice-center competition. One commissioner described the selection process as lengthy and closely contested: "It was a long day, a lot of discussion, a lot of questions," a commissioner said during remarks.

The Fentress Studios award covers early-phase services; the county will negotiate any additional fees and scopes after conceptual work. The asphalt and crack-seal awards are single-year supply contracts for 2026 with the amounts and vendors announced during the meeting.

Next steps: contract documents and any required signing will follow departmental procurement procedures and the board's motions recorded at the March 2 meeting.