Council rejects lone bid for Rock Run Embankment, orders re-advertisement
Summary
RK&K engineer Matthew Goudy told the council the single bid for the Rock Run Embankment Project from Lindstrom Excavating was $377,225, higher than expected. Council voted unanimously to reject the bid and re-advertise with amendments to the bid package to encourage more bidders and lower cost.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Town engineering consultant Matthew Goudy (RK&K) reported to the Port Deposit Town Council that only one bid — from Lindstrom Excavating Company — was received for the Rock Run Embankment Project, at $377,225, which he said was significantly higher than anticipated.
Council discussed options to reduce cost and attract more bidders, including removing the mandatory pre-bid meeting requirement, considering alternate materials and pursuing a permit modification to allow a temporary stream crossing. Councilman Tom Knight moved and Councilwoman Randa Thiele seconded a motion to reject the bid and re-advertise the project with amendments to the bid package; the motion passed unanimously.
The Council provided direction to staff and the consultant to revise the specifications and rebid the project. No further contract action was taken at the meeting; staff will return with amended documents and an updated procurement timeline.