Norton board approves paving change order, bridge joint work and museum roof contract
Summary
At its May 4 meeting the Board of Control approved a $24,461 change order for the 2025 paving program, a $13,140 contract to replace pressure relief joints on the Clark Mill Road Bridge and a $20,970 roof-and-gutter replacement at the Berry House Historical Museum; all motions passed by recorded roll call.
Get email alerts on the Public Works Contracts topic
No spam. Unsubscribe anytime.
The Board of Control (Norton City Council) on May 4 approved three maintenance contracts intended to address failing pavement bases, a bridge joint problem and a leaking historic roof, with the three actions totaling $58,571.20.
A city staff member told the board crews found the pavement base under sections of the 2025 paving program to be “in pretty bad shape,” and said the engineer recommended thickening the intermediate asphalt course from one-half inch to one inch to improve the integrity of new paving. The board approved change order No. 1 for the 2025 paving road program with Barbicas Construction Company in an amount not to exceed $24,461.20.
The board next approved a contract with Barbicas Construction Company to perform a pressure relief joint replacement on the Clark Mill Road Bridge for an amount not to exceed $13,140. Staff said the work will likely require temporary road closures on Clark Mill Road, that only one local firm submitted a quote, and that the approach conditions at the bridge are severe enough to jar vehicle occupants and warrant repair.
The third action awarded Daryl Yoder Roofing the contract to replace the roof and gutters on the Berry House Historical Museum in an amount not to exceed $20,970. Staff said the roof is leaking and failing; the city has an agreement with the historical society to maintain the property. The board moved and seconded the award after staff reported additional work was needed beyond the original quote.
Votes at a glance - Change order: 2025 paving (Barbicas Construction Company) — approved; amount not to exceed $24,461.20. Recorded votes (yes): Mr. Herbert; Mr. DeHart Part (transcript spelling); Mayor Zita; Mr. Orr; Ms. Keener. - Clark Mill Road Bridge joint replacement (Barbicas Construction Company) — approved; amount not to exceed $13,140. Recorded votes (yes): Mr. Herbert; Mr. DeHarpart/De Harper (transcript variants); Mayor Zita; Mr. Dorr/Orr; Ms. Keener/Kiner. - Berry House Historical Museum roof and gutters (Daryl Yoder Roofing) — approved; amount not to exceed $20,970. Recorded votes (yes): Mr. De Harper (transcript variant); Mr. Herbert; Mayor Zita; Mr. Rohr; Ms. Kiner (transcript variant).
The board also approved the April 20, 2026 minutes as submitted and adjourned at 6:10 p.m.