Gilroy Unified outlines storm repairs, authorizes bids for freezer, restroom and fire‑alarm projects
Summary
Facilities staff described storm‑related roof and water damage at multiple campuses and presented capital projects (Luigi AA walk‑in freezer, district warehouse GMP, transportation yard restrooms, Mount Madonna fire‑alarm upgrade). The board authorized solicitation of bids and approved a $280,000 contract amendment to add two wellness coaches (total not‑to‑exceed $600,000).
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
District facilities and maintenance staff reported on storm damage and active capital projects and the board authorized solicitations for several campus projects on March 20.
Facilities Director Paul Nato outlined three projects in design or pre‑construction: a walk‑in freezer and related site reconfiguration at Luigi AA Elementary; pre‑construction work and a developing guaranteed maximum price for the district warehouse with Flint Builders; and a restroom installation and site upgrades at the transportation yard. Facilities staff also said they will upgrade the fire‑alarm system at Mount Madonna over the summer.
Maintenance reported extensive storm response since early February: staff responded to dozens of roof leaks across multiple campuses and performed emergency drying and temporary repairs. Christopher High School’s Building E suffered multiple water entry points that affected several rooms; staff have abated water intrusion, moved impacted classes and are seeking quotes for permanent repairs and roof replacement.
The board also approved a contract amendment with Effective School Solutions to add two full‑time, non‑clinical wellness coaches (for Christopher High and Brownell Middle School), increasing the previous contract by $280,000 to a not‑to‑exceed $600,000. Director of Student Services Anna Poo described the wellness‑center staffing models and grant sources used to fund wellness personnel districtwide.
Finally, the board approved resolutions to solicit bids for the Luigi AA walk‑in freezer, Mount Madonna fire‑alarm upgrade and transportation/maintenance yard restroom project by roll‑call vote.