Hagerstown withdraws make‑whole electric rate filing after PSC spreadsheet error; staff to pursue full cost‑of‑service study
Summary
Utility staff told the council that a November make‑whole filing was reduced during PSC review and settlement negotiations; a PSC spreadsheet error further reduced the figure and led the city to withdraw the application. Staff plans a new cost‑of‑service review and will seek roughly $100,000 in consulting funds for that study.
Get email alerts on the Utilities topic
No spam. Unsubscribe anytime.
City utility staff provided an update on the electric retail operating rate case at the April 7 work session. The city’s November make‑whole filing sought roughly $735,000; PSC technical staff’s review reduced adjustments to a $646,000 figure and settlement discussions produced a $477,000 number. A PSC spreadsheet error discovered just before a hearing recalculated the numbers to about $235,000, prompting the city to withdraw the application.
The presenter identified as "Mr. N." told councilmembers the PSC judge questioned the basis for a so‑called ‘‘blackbox’’ settlement that offered a single number without publicly documented calculations. Because of those concerns, the city withdrew the filing and intends to commission a full cost‑of‑service study using the latest audited financials.
Staff said the administration will come back seeking approval to contract GDS & Associates (and related consultant funds of about $100,000) to complete the study; once the cost‑of‑service work is complete staff will return with a recommended filing. No vote occurred at the work session.
Ending: Council members were informed of next steps: staff will seek authorization for consultant services and report back with cost‑of‑service results before a future filing.