Wylie awards $3.16M design contract to advance Kramer Lane widening; city share about $1.56M

City of Wylie City Council · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a $3,163,380 professional services agreement with Teague, Noll & Perkins for design of Kramer Lane and Troy Road widening; federal funding covers roughly 80% of construction and the city’s design portion is $1,564,510.61, with Collin County cost sharing.

The Wylie City Council voted 7–0 on May 12 to authorize a professional services project order (PSPO W2025-98) with Teague, Noll & Perkins for design of the Kramer Lane/Troy Road widening and improvements.

City staff described a roughly 7,000-foot corridor project that will widen Troy Road and convert Kramer Lane to a four-lane concrete roadway in parts of the city. Staff said the project previously received federal funding approval on an 80/20 split for construction; the city chose to remove the design phase from federal funds to accelerate the schedule and start design immediately.

The total design contract amount is $3,163,380. Of that, the city’s share is $1,564,510.61 and Collin County’s share $1,598,869.39 under an interlocal cost-sharing arrangement. Staff said federal construction funds of about $23,000,000 are anticipated in 2028–29 for the construction phase. The contract includes an 800-day schedule (design through construction) with a 6–9 month allowance for utility relocation.

Council asked about budget line items and staff explained the city portion is funded from restricted impact-fee accounts reserved for infrastructure in the project area. After Q&A about the consultant’s responsibilities for right-of-way, permitting and utility coordination, Mayor Pro Tem moved to approve the contract; Council voted unanimously.

The contract authorizes city manager execution of documents necessary for design to proceed.