Cresco council weighs large cost increase for Castle Lodge parking-lot work; asks for asphalt vs. concrete estimates

Cresco City Council · July 15, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council members reviewed uncompleted capital projects and learned the Castle Lodge parking-lot removal could add roughly $177,000 to the previously approved budget, prompting a request for additional estimates (including asphalt alternatives) and a follow-up on Aug. 5.

Council members spent a substantial portion of their July 15 meeting reviewing uncompleted capital projects and a possible budget amendment after staff highlighted several items that exceeded earlier estimates.

The most significant point of contention was a concrete parking lot by Castle Lodge. Staff said removal of existing concrete — which had not been included in prior estimates — adds about $177,000 to the project cost; when combined with replacement the staff discussion suggested total costs could approach roughly $880,000. Council asked staff to obtain a second opinion and a specific asphalt-vs-concrete cost comparison for the Aug. 5 packet before any budget amendment is considered.

During the exchange staff and council discussed unit-cost figures offered in the meeting: one contractor estimate mentioned asphalt at roughly $20–$30 per square yard (for a 4-inch depth) and cited concrete near $50 per square yard; another staff comment referenced a figure of about $135 per cubic yard in a different context. Council members cautioned that while asphalt may be cheaper up front, concrete can last longer and patching costs differ; they emphasized evaluating lifecycle and the condition of adjacent roadway segments before deciding.

Staff said most other uncompleted projects generally matched prior budgets, but a few unexpected expenses and donated items changed some line-item balances. Administration and finance staff noted some revised packet materials were missing from the revised packet distributed before the meeting and that the full fund-balance detail would be included in the next packet.

Council directed staff to: • Seek a contractor estimate on asphalt versus concrete alternatives for the Castle Lodge parking lot; • Include the contractor’s and staff’s findings in the Aug. 5 packet for council review; and • Re-present any proposed budget amendments with detailed line-item impacts before any vote.

The council did not adopt a budget amendment at the July 15 meeting; it agreed to revisit the packet on Aug. 5 with additional information.