Board reviews facilities master plan and hears update on Northeast Middle-High School project opening in 2027
Summary
The board received the FY27 Educational Facilities Master Plan for review and an update on the new Northeast Middle-High School, including a July 1, 2027 projected opening, a 1,000-seat auditorium and pending road-widening approvals; a $135,787.27 roofing change order was approved.
Get email alerts on the Facilities Master Plan topic
No spam. Unsubscribe anytime.
The Cecil County Board of Education on May 13 received the FY27 Educational Facilities Master Plan for review and heard a progress report on the new Northeast Middle-High School, set to open July 1, 2027.
"That is the new Northeast Middle High School set to be open 07/01/2027," Superintendent Dr. Lawson said while showing renderings and construction images. Facilities staff described the building layout — separate middle- and high-school wings, a shared kitchen and a planned 1,000-seat auditorium — and said the building will sit on a hillside with pedestrian "Main Street" circulation between wings.
Executive Director for Facilities Dr. Ted Boyer described the master plan as the district’s "go-to book" for facilities and capital planning and recommended board members review the nearly 200-page document, calling attention to a one-page summary of all schools on page 52. "This document explains how we use our facilities, evaluates them, and identifies needs," Dr. Boyer said; the master plan will be held over for one month before a formal vote.
The board approved a roofing change order to reconcile the RFP and final structural design for the Northeast Middle-High School replacement project. Facilities staff recommended amending RFP 24-15 to include the presented change order for a total of $135,787.27; after a motion and second the motion carried.
Facilities staff also noted pending state approvals needed to begin widening Irishtown Road to accommodate the new campus’s bus loop and drop-off configuration. During the presentation, staff described building components including the auditorium, cafeteria/media center, gym, HVAC penthouse area and walkways connecting floors.
The board did not vote on the master plan on May 13; staff asked members to submit questions by email and indicated the plan will return for a vote at the next month’s meeting after member review.
Next steps: Board members will review the facilities master plan during the month and the district will await state approvals on roadway work before beginning road widening this summer.