Summary
The Commission reviewed Monroe Township's 2025 housing element and Hightop redevelopment plan (26 acres) and staff reported the plan meets CMP standards provided infrastructure is verified; the township proposes up to 11 units per acre with a 20% affordable set-aside and staff said estimated flows would not exceed a 3.0 mgd wastewater cap under an existing MOA.
Get email alerts on the Housing Redevelopment topic
No spam. Unsubscribe anytime.
Commission staff presented Monroe Township's 2025 housing element and the Hightop redevelopment plan to the Pinelands Commission on May 8 and recommended certification of the plan to the full Commission.
The Hightop redevelopment area is a 26-acre site in the township's regional growth area at the edge of the Pinelands preservation boundary. Under the redevelopment plan, the township would change permitted uses to allow a mix of commercial and residential development, including townhouses and multifamily units, with residential densities up to 11 units per acre. The redevelopment plan would require a 20% affordable set-aside, which staff said could deliver up to 48 affordable units; the plan also allows buildout up to 286 units overall, a figure that exceeds CMP minimums but is permitted if infrastructure and environmental standards are satisfied.
Staff noted an existing memorandum of agreement between the Pinelands Commission and the Monroe Township MUA that caps wastewater leaving the Pinelands area at 3.0 million gallons per day. Using staff estimates of full buildout demand, staff concluded the Hightop plan would not be anticipated to exceed that 3.0 million gallon daily limit and that no additional monitoring trigger was expected. Staff also reported no significant wetlands on site and described limited transition-area vegetation, and said mandatory PDC (Pinelands Development Credit) requirements would apply to market-rate units with exemptions for affordable units up to 48.
Commissioners moved and seconded consideration of the plan; a vote was taken and staff reported a finding that the housing element, fair-share plan and redevelopment plan comply with Comprehensive Management Plan standards. The transcript does not provide a line-by-line roll-call tally in numerical form. Commissioners asked about infrastructure verification and monitoring obligations tied to the MOA; staff said they had estimated demand and would continue to track flows under the existing agreement.
The Commission's review will be reflected in staff reports and, where applicable, in the certification materials and conditions of any future approvals. Commissioners also discussed the broader role of municipalities in using density incentives in regional growth areas to meet affordable-housing obligations and flagged remaining checks on infrastructure adequacy.