Summary

Staff presented quotes from ADE Construction to replace and upgrade a water main as part of the Park/Orange/Crystal streetscape project (quoted around $581,097). Staff said the work is necessary to avoid re‑excavating after streetscape completion and noted irrigation sleeves will be installed; funding sources and use of impact fees were discussed.

City staff told commissioners a water‑main relocation and upgrade associated with the Park/Orange/Crystal streetscape is necessary now to avoid later re‑excavation, and presented contractor quotes for consideration.

Sarah Kirkland, the city’s public works director, said the contractor returned a quote “somewhere around” $581,097 to replace and upgrade the water main that runs from Market Street to Crystal and down Orange Avenue; the work includes irrigation sleeves for future landscaping. She explained the timing is tied to the streetscape contractor’s excavation and that completing the water main work now avoids having to tear up finished streetscape later.

A property owner raised a related alley sewer issue and urged the city to include those older cast‑iron pipes in future budget planning; staff said sewer replacements are planned separately but acknowledged the long‑standing risk in older alley infrastructure. The public works director also said impact fees could be used to cover part of the upgrades, noting staff had discussed the option with the appropriate finance staff.

Commissioners did not take immediate action at the work session; staff indicated the quotes are coming before the commission for approval and that funding sources have been identified as part of the capital plan.