Lafayette Waterworks declares phase one of lead service line replacements substantially complete; retainage held

Lafayette City Council · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Lafayette Waterworks staff presented a substantial-completion certificate for phase one of lead service-line replacements completed by Atlas Excavating on April 3; the council approved the certificate while holding $126,000 in retainage pending completion of remaining punch-list items.

Steve Moore, superintendent of Lafayette Waterworks, recommended the council approve a substantial-completion certificate and punch list for the phase-one lead service-line replacement project. Moore reported that Atlas Excavating achieved substantial completion on April 3 and that the city is holding $126,000 in retainage, which he said equals about 200% of the value of the remaining punch-list items.

Moore recommended approval of the certificate while retaining the holdback until the remaining items are finished; the council approved the recommendation by voice vote. Moore said the retainage will be held until the outstanding punch-list items are completed and verified by the inspector.

Next steps: Atlas Excavating will complete punch-list items, after which staff can recommend release of retainage if the work meets contract terms.