Development committee approves negotiated contract for Horizon South–Chamberlain Connector
Summary
The Development & Planning Services Committee approved a negotiated construction contract with Garrick Civil Works for the Horizon South–Chamberlain Connector, reducing the low-bid gap from about $18.2 million to roughly $15.0 million after value engineering; the contractor will have 600 days from notice to proceed.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
The Development & Planning Services Committee on May 12 approved a negotiated construction contract for the Horizon South–Chamberlain Connector after staff and the low bidder modified the project's scope through value engineering.
Mr. Titus, presenting the project, told the committee that the initial bid process produced a low bid that exceeded budget (about $18.2 million). After negotiations and modest design revisions intended to preserve the overall design intent, the county reached agreement with Garrick Civil Works on a negotiated construction price of $14,991,882, to be funded from SPLOST funds, with a contract time of 600 days from notice to proceed.
Titus said the corridor will connect Chamberlain Road to Horizon South Parkway and include a roundabout and a roughly 500-foot bridge crossing a creek; staff noted the bridge work will be on the project's critical path. "We still have the overall design intent the same…we've negotiated with them… $14,991,882," he said.
Committee members described the project as likely to relieve traffic across multiple nearby roadways and moved the item to consent for approval. Staff said construction timing is weather-dependent and estimated completion in late 2028 to early 2029.
The committee approved the consent motion; no roll-call tallies were recorded in the transcript.