Commissioners approve five change orders to finish Bridge 56 project
Summary
Howard County commissioners approved five change orders to wrap up Bridge 56 on 300 East near Sycamore, citing stormwater work, unexpected pier deterioration and subgrade replacement; the total amount read at the meeting contained unclear digits and is noted as stated.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Howard County commissioners on Jan. 20 approved five change orders to finalize a repair project on Bridge 56, the bridge on 300 East just south of Sycamore, county highway staff said.
Amber Tol of the highway department told the board the project reopened around Thanksgiving but work uncovered additional needs. Change order two was described during the meeting as an overrun to storm-water management due to adding a second causeway after heavy June rain. Change order three addressed unexpectedly deteriorated piers that required removal and replacement of additional material. Change order five related to bad subgrade discovered when workers removed road material.
Tol said not all five change orders carried monetary costs; one was a federal paperwork/item-name correction and another was a non-monetary schedule change to accommodate federal approvals. Tol said the change orders are included in the bridge budget and requested commissioner approval.
The board moved, seconded and approved the five change orders by voice vote. The dollar amounts read aloud in the meeting record included several figures that were unclear in the live transcript (for example, the clerk read amounts as "$23,3361" and "$8,82245" and a total of "$68,95046"). Because the meeting audio/recording contained unclear numerals, the county clerk should be consulted for the official, itemized change-order amounts and the signed change-order documents.
No additional discussion or legal caveats were recorded; the chair requested signatures to complete the paperwork.