Commission approves $500,000 change order for amphitheater parking; commissioners debate regional priorities

Bernalillo County Board of Commissioners · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works reported crews encountered buried solid waste while constructing access to the Salida/Journal Pavilion parking lot; a $500,000 change order (adding 12 days) funded by Live Nation revenue‑sharing and reserves brings the project to roughly $3.0M and was approved 3–2 amid questions about prioritizing East Mountain road projects.

Bernalillo County Public Works told commissioners that construction of the Salida/Journal Pavilion amphitheater parking lot hit an unexpected abandoned‑landfill cell; crews excavated roughly 3,000 cubic yards of solid waste and must transport it to an out‑of‑county landfill, creating a change‑order request of just under $500,000 and a 12‑day schedule extension to the $2.5 million project.

Technical services director explained the geotechnical work included more than 30 borings but that an 800‑foot gap between borings missed the landfill material encountered during construction. Project costs will be covered largely by revenue‑sharing from Live Nation, with some project reserves covering additional expenses.

Commissioners asked about the project’s timeline and service life and raised competing regional priorities, noting that the county’s East Mountains roads have acute needs and that the $500,000 change order roughly equals the earmark for that region’s road work. Public Works staff said the work should provide a reasonable service life and that the parking/additions will also serve adjacent recreational facilities.

After discussion, the commission approved the change order by roll call, 3–2.