Waverly utility staff brief board on new state load-forecasting requirement and estimated costs

City of Waverly Utilities Board · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the board a recently passed state economic development bill requires utilities to file load forecasts with a first reporting deadline of Dec. 31, 2028; staff expects to hire a consultant at an estimated $5,000–$10,000 every two years and an Iowa State University administrative fee roughly 0.02% of prior-year revenue.

Utility staff briefed the City of Waverly utilities board on a new requirement created within a recently passed state economic development bill that will oblige electric utilities to file load forecasts.

Director (speaker 6) said the bill requires a load forecast based on prior-year numbers, with the first reporting period due by Dec. 31, 2028 (reporting 2027 numbers). "We're probably gonna bring a consultant in to do that. Similar to what we do like a cost of service study," the director said.

Staff estimated the consultant work would likely cost in the $5,000–$10,000 range every two years; they also said Iowa State University is expected to assess an administrative fee to participating utilities, which staff described as approximately 0.02% of the previous year's revenue. Staff said the forecasting data will be aggregated and submitted through the state process to inform longer-term planning for generation and transmission needs.

Board members asked about comparability to peer utilities and potential risks; staff and the auditor noted that utilities vary and cautioned comparisons can be imprecise. Staff said they will return to the board with additional details and likely a plan to procure consultant services when regulatory guidance is finalized.