Commission reviews design and timeline for Lions Wayside Park and 436 First Street improvements

Pleasanton Commission · May 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners reviewed a $240,000 plan funded by park impact fees to build a 24‑stall tree‑lined parking lot, trail connection to Firehouse Arts Center, lawn conversion for concert viewing and reserved space for future improvements; construction is scheduled to begin in June with parts open by July 11.

Pleasanton staff presented conceptual designs May 8 for finishing work at Lions Wayside Park and for improvements to a city‑owned property at 436 First Street, proposing to spend roughly $240,000 in dedicated park development impact fees on a parking lot, pedestrian trail, lawn conversion and a reserved 5,000‑square‑foot parcel for future amenities.

City landscape staff (presenter identified as Matt) said the funds became available after competitive bids for the larger Lions Wayside project came in under estimate. The proposed work would: construct a 24‑stall, tree‑lined parking lot with bioretention; build a pedestrian/trail connection to the Firehouse Arts Center parking lot; convert adjacent turf to a secondary concert viewing lawn; and reserve a 5,000‑sq‑ft area for a future playground or other recreation feature.

Timeline and operations: staff said construction for the parking, trail and lawn conversion would start in June, with the park improvements opening in time for the summer concert series (target opening July 11) and final items finishing by August–September. Staff noted restrooms are not included (estimated basic restroom costs exceed the available budget) but the reserved 5,000‑sq‑ft area could accommodate future restrooms or a playground if funds become available. The project avoids creek work to minimize regulatory permitting requirements.

Commissioners generally supported the concept and raised questions about temporary event access (food trucks), restroom proximity for larger crowds, creek permitting constraints and the potential for sponsorships to fund later phases. Staff said the parking lot and trail are flexible and could be used for temporary event vehicle access and that Lions Club fundraising and sponsorship policy could help future amenities.

Next steps: staff requested commissioner comment on the designs and plans to return to City Council in June to approve contingencies and construction authorization.