Board awards $3.96 million renovation contract for Parks & Recreation campus; construction to start June 1

The Woodlands Township Board of Directors · April 23, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Woodlands Township approved a base construction contract of $3,964,877.42 (with related furniture and contingency funding) for renovations to the Parks & Recreation campus, with construction targeted to begin June 1 and substantial completion expected by March 2027.

The Woodlands Township Board of Directors on April 23 voted to award the construction contract to Anchor Construction for renovation of the Parks & Recreation Campus. The base bid for construction is $3,964,877.42; when combined with office furniture ($260,703.33) and previously approved design/management costs, staff presented a total project value in the packet and identified a contingency reserve.

John McGowan, director of Parks & Recreation, walked the board through the project scope: roughly 4,500 square feet of added space, 42 additional parking spots, renovations to two existing buildings, more meeting rooms, expanded break areas, a new staff entrance and improved parking lot flow. McGowan said about 133 employees are based in the buildings and the renovation would shorten staff congestion and permit temporary trailers during construction.

Budget and timeline: the staff packet included a project budget figure and showed the bid tabulation: the base bid ($3,964,877.42), office furniture ($260,703.33), and a project contingency of roughly $524,629 (numbers presented in staff materials). McGowan said construction would begin June 1 with nine months of construction activity and a substantial-completion target of March 2027.

Board action and rationale: after questions about furniture disposition (required auction per policy) and construction phasing to keep operations running, a motion was made and seconded to award the contract and authorize the CEO to execute necessary documents. The motion carried on voice vote.

What residents asked: board members asked about temporary workspace arrangements, disposal/auction of existing furniture, exterior materials (metal building), and maintaining operations during construction; staff said many staff will relocate to temporary trailers and that surplus furniture will be auctioned per the township’s legal/public process.

Next steps: staff will finalize contracts with Anchor Construction and manage mobilization to meet the June construction start date. The board authorized use of contingency funds for necessary change orders and testing within authorized spending limits and directed staff and legal counsel to finalize contract documents for execution.