Votes at a glance: committee approves technology, site work, landscaping conditional‑approval and Cox connection

Newport Building Committee · July 2, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A concise list of motions and outcomes from the Newport Building Committee meeting: the committee approved owner‑supplied technology ($1,334,135.89), multiple ATP/RTA packages (site concrete, landscaping conditionally, final cleaning), granted change‑order authority up to $25,000 for the summer, and approved a Cox service agreement; several alternates were held for later pricing.

At its meeting the Newport Building Committee took the following formal actions (all motions passed by voice vote unless noted):

- Owner‑supplied technology equipment — Motion to approve owner supply technology equipment at $1,334,135.89 (funded from the technology budget). Outcome: approved unanimously. (Discussed: need to meet an Oct. 15 target for internet/Wi‑Fi readiness.)

- ATP 65 / RFI 289 — Add fire alarm devices (price recorded in transcript as an RFI/ATP addition). Outcome: approved unanimously for code compliance.

- ATP 68 (Bulletin 21) — Credit for removing specified items; credit recorded as $80,825. Outcome: approved unanimously.

- ATP 74 (Bid package Phase 1B) — Phase 1B site work including west parking lot asphalt, north parking lot striping and sidewalk prep; staff said this is part of the TCO critical path. Outcome: approved unanimously.

- RTA 3B rev.1 (site concrete) — Presented at $710,000; includes alternates and a recommended $5,000 allowance for a brick‑veneer shelf. Outcome: approved unanimously; some alternates to be reconciled with the mason later.

- RTA 32A rev.1 (landscaping) — Presented at $710,241; motion included conditional approval subject to the landscaper holding pricing. Two value‑engineering deducts were discussed: Alternate 9 (remove granite flag‑pole base, approx. $66,000 credit) and Alternate 10 (defer site furnishings, approx. $175,000 credit). Outcome: landscaping approved conditionally with Alternate 10 removed from the immediate scope and Alternate 9 held for staff to return with smaller/alternative granite options and pricing.

- RTA 01B rev.1 (final cleaning) — $225,000. Outcome: approved unanimously.

- Change‑order review committee authority — Motion to allow the review committee to approve change order requests up to $25,000 each (summer); intended to reduce delays when a quorum is not available. Outcome: approved by majority voice vote.

- Cox Communications service agreement — Fee recorded as $11,282.77 to pull fiber/telephone feed from the road into the building. Outcome: approved unanimously.

Notes: Briggs (third‑party testing and inspections) notified staff of a requested 4.5% annual rate increase; staff will return with recommendations. Several contract amounts and alternate credits were discussed during debate and some items were held or conditioned on price holds as noted above.