Pilgrim and Tollgate projects on track; committee schedules special meeting to review CD packet
Summary
Project managers reported Pilgrim design review with the School Building Authority and steady draft cost estimates; teams recommended adding underslab radon mitigation and possible NCAA-sized basketball courts; a special committee meeting was scheduled for March 19 to review construction documents and bid packets.
Get email alerts on the Pilgrim Project topic
No spam. Unsubscribe anytime.
Project staff updated the committee on high-school construction projects and said Pilgrim High School remains on budget and on schedule for the next design review.
Mr Bates told the committee the Pilgrim design team had a final design progress review scheduled with the School Building Authority and that draft cost estimates for the 60% drawings remained aligned with prior estimates. He said the team is studying a passive underslab radon mitigation system, an option that is less expensive to install now than to retrofit post-construction.
Architects are also evaluating whether both high-school gyms can be enlarged within existing footprints to provide NCAA-size basketball courts, an adjustment that would add roughly 5 feet on each side of the court if feasible and not materially increase cost. Mr Bates said bid competition to date has produced numerous bidders (12 respondents for a recent steel bid), which the project team said generally lowers prices.
A special school-committee meeting was scheduled for March 19 at 5:30 p.m. to review the construction documents and the bid packet for Pilgrim; the building committee will hold a morning session the same day. Officials said third-party estimates required by RIDE are forthcoming and that administration will provide CD packets to committee members in advance to allow review before the special meeting.