Carbondale Aquatic Center to open May 23; officials say project remains on budget
Summary
Town staff and project representatives reported the Carbondale Aquatic Center is finishing punch-list work, is staffed for the season and will hold a grand opening on May 23; officials said the project is tracking within the $13,419,000 budget and a test day is scheduled ahead of opening.
Get email alerts on the Infrastructure Recreation topic
No spam. Unsubscribe anytime.
Town staff and project representatives gave trustees a detailed construction and operations update on the Carbondale Aquatic Center, saying finishing work is underway and the facility is on schedule to open.
A project representative described punch-list activity — masonry and cleanup, landscape preparation and final installations — and said contractors report they have the materials and are productive on-site. The representative said staff have run one change order and that the work is not expected to increase the guaranteed maximum price materially.
Eric, the aquatics lead, said lifeguard and water-safety training have been completed and a test run with lifeguards and volunteers is planned this weekend to verify showers, systems and staffing. "Carbondale Aquatic Center grand opening, Saturday, May 23, 12 to 6PM," Eric said, inviting the public to opening-day events including contests and giveaways.
Officials discussed season length, winterization and how the facility’s heat systems (referred to as "big boppers") affect shoulder-season operations. Eric said staffing had been a tight issue but that the department is now fully staffed to hold the published schedule; he said the town will finalize the summer schedule once training is fully complete.
On budget, a project representative reiterated confidence the project will finish within the reported $13,419,000 figure and characterized recent probable change orders as small and manageable.
Trustees asked about aesthetic punch-list items and accessibility of additional park space for special events; staff said those operational details would be handled through event planning and temporary measures when needed. The board did not take formal action during the report; the facility opening and a donor event were scheduled in the coming week.