Homer Glen amends local match cap for 100 51st Street reconstruction after trustees question estimate
Summary
Trustees voted to authorize local matching funds to secure roughly $5.66 million in federal and state funding for the 100 51st Street reconstruction but amended the resolution to cap the village’s contribution at $2,000,000 before additional approvals, citing questions about the open-ended language and engineer estimates.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Trustees approved a resolution authorizing the village to provide local matching funds to secure federal and state grants for the 100 51st Street reconstruction project, but they amended the authorization to include a $2,000,000 cap on the local match before the board would be asked to reconsider larger commitments.
Trustee Lepore pressed staff on the math, citing the packet language that the village had received $5,659,976 in federal and state grants and that the local match should be roughly a 20 percent share. Lepore asked why the draft resolution authorized up to $1,819,088 when a straight 20 percent of the grant figure would be lower; Director Westcott said the larger authorization included prior design-phase costs and other earlier expenditures that affect the total match calculation. “This is strictly for phase 3 construction,” Westcott said, adding that the resolution reflected an engineer's estimate and that final local match will be determined after bids are received.
Several trustees expressed concern that the language “as much as may be needed to match federal funds” left the village open ended. After discussion, the board approved an amendment to the resolution that requires the village to cap its local match at $2,000,000 before any additional funds would be committed without returning to the board for reconsideration.
Director Westcott said design work for phase 2 is about 95 percent complete and that construction would likely not begin until 2027 because of utility relocations and coordination with other county work. He said the project will upgrade the corridor between Parker and Bell Road to a three-lane section with curb and gutter and drainage improvements intended to reduce congestion and address sight-distance issues.
The amended resolution passed by roll call. Trustees said they expected IDOT and state procedures would still allow the village and state to reconcile final numbers after bids are opened and that a cap gives the board greater control if costs greatly exceed the engineer’s estimate.
Next steps: staff will submit the amended authorization to IDOT and continue finalizing bid documents and utility coordination; construction is likely to follow in 2027 pending utility work and contractor scheduling.