District presents science-room repairs, parking-lot repaving options and fiber run quote

Tomorrow River School District Board of Education · June 18, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board heard contractor quotes to repair unexpected structural issues in the science room, discussed full and partial north parking-lot repaving options (with a full-replace estimate near $123,000) and reviewed a $7,416 Total Electric quote to run 12-strand fiber to the stadium.

Project staff updated the board on several facility projects and quoted costs at the meeting.

Science room structural work: presenters described unanticipated joist-bearing conditions that required cutting the wall and reinstalling block and other repairs. Vendors provided line-item quotes for concrete, masonry and steel work and a contractor submitted a 'not to exceed' price to address unknowns; backup documents with detailed quotes had been provided to board members. Project staff recommended a repair option that avoids an exposed interior column by inserting block and filling the wall.

North parking lot: staff presented options to pulverize and repave 4,956 square yards and an alternate scope that would replace 5,959 square yards. The full-replace option was discussed at approximately $123,000; staff cautioned that any work requiring replacement of base material could trigger a new stormwater-management plan and additional permitting.

Lighting: the board discussed re-adding six parking-lot lights removed during earlier value engineering. Total Electric provided an estimated cost to reinstate those lights; staff noted the lights would improve safety and would be placed near the new STEAM center, the elementary, and the road entrance.

Fiber run to stadium: an updated Total Electric quote of $7,416 was reported to replace an existing six-strand run with a 12-strand fiber; some board members questioned replacing functioning fiber absent a demonstrated failure.

Budget context: staff reviewed contingency and interest-earnings figures, listing planned uses from referendum and interest funds (Wi‑Fi access points, smartboards, cameras, furniture and appliances) and reported a remaining balance of roughly $588,000 after the listed allocations.

Next steps: staff will proceed with the chosen repair scopes and provide final contract documents for board approval when available; any scope that requires base replacement will trigger additional permitting and cost review.