Wauwatosa finance committee reviews 2024 referendum progress, roofing work and new public dashboard
Summary
District staff told the Finance & Resource Committee that phase‑one safety documents will go out this month, roofing removal began June 17 at Eisenhower, bids are running under the referendum contingency and a public dashboard now shows per‑building spending and project details.
The Wauwatosa School District Finance & Resource Committee heard a detailed update July 16 on implementation of the 2024 referendum, including roofing work now under way, ongoing schematic design for phase two and a new public dashboard that will show building‑level spending and project status. The committee approved minutes at the start of the meeting.
Staff said the district has posted the June referendum update to the website and that phase‑one construction documents — focused on safety work — will be released this month. On roofing, the presenter reported that removal began June 17 at Eisenhower and crews have proceeded with staging,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat