Engineering outlines multi-year water and wastewater capital projects; filter rehab and headworks screening among priorities

Public Works Advisory Committee · March 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineering presented a multi-project update including a new alluvial well (Well 6), filter rehabs and valve-control upgrades at the water plant, an RO skid replacement, and wastewater headworks, sludge handling and clarifier rehab projects; several items are in construction or design.

The Public Works Advisory Committee received a wide-ranging water and sewer project update on March 19 from Sean Singer, the city's engineering manager for water and sewer.

Singer said three major water-side projects are in construction, including a new alluvial well (Well 6) on plant property and filter rehabilitation work that recently completed sampling and is being returned to service. He described a parallel controls and valve replacement project intended to protect the filter investment and avoid future catastrophic backwash failures.

Singer said the city will open bids on a reverse-osmosis (RO) skid replacement and chemical-feed upgrades to address equipment reaching the end of its useful life. He also described early design work on front-end oxidation improvements to remove iron and manganese so filters run longer between backwashes, and a chloramine conversion for in-town wells to align disinfectant residuals across interconnections.

On the wastewater side, Singer described work on a new dual-screen headworks to reduce hair- and rag-related maintenance problems, sludge handling upgrades (including consideration of centrifuges or presses to improve dewatering), grid system conversions to increase removal efficiency, clarifier rehabilitations planned in phases, lift-station upgrades, odor-control work shifting from carbon scrubbers to bio-scrubbers, and various safety and access improvements.

Singer said most recent bids have come in near budget and that long lead-time supply issues have moderated since pandemic-era peaks. Several projects are at 30% design or early procurement; the committee asked technical and funding questions and staff agreed to follow up with additional documentation as projects progress.

No binding votes were taken during the update; the briefing was informational and focused on project sequencing, procurement and lifecycle replacement needs.