Mil Creek council accepts 2026 pavement preservation bid and authorizes construction management for catch-basin repairs

Mil Creek City Council · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Mil Creek City Council voted May 12 to accept a low bid for the 2026 pavement-preservation project and to authorize a construction-management contract for a multi-year catch-basin repair program. Both motions passed unanimously.

The Mil Creek City Council voted on May 12 to accept a responsive low bid for the city's 2026 pavement preservation program and to authorize a construction-management agreement for a citywide catch-basin repair and replacement effort.

Pavement preservation: Project engineer Robert Bean told the council the preservation program focuses on roads with pavement condition index scores requiring grind-and-overlay (mill-and-fill) work and includes ADA curb-ramp upgrades. Bean reported the original program budget at $2,921,000 and that design and advertisement costs to date totaled about $291,000, leaving roughly $2.6 million available. The engineers’ estimate for construction work was about $1.32 million and staff reported a responsive low bid of approximately $1,273,306.50 (inclusive of tax). Council moved and unanimously adopted a resolution to accept the bid from Granite Construction Company for a contract not to exceed the stated bid amount.

Catch-basin repair and replacement: City engineer Dan Cardy and project engineer Robert Bean described a multi-year program that identified 1,011 catch basins needing repair; 482 of those require multiple repair actions. The engineer's construction estimate was $6.9 million; one responsive construction bid (Earthwork Solutions) was reported at roughly $5.4 million. Council authorized the city manager to execute a construction-management contract with KPFF Inc. to provide preconstruction and construction-management services for up to $848,725.32 (including sales tax). Staff characterized KPFF’s fee as about 15.6% of the construction cost, noting that KPFF scored highest in experience and scheduling ability for this city's delivery timeline. The council approved the motion by voice vote.

What this means: Staff said the pavement work is expected to be substantially complete by early September to allow for striping late September–early October; catch-basin repairs are scoped over a three-year timeline, with the contractor indicating confidence in completing much of the work in 20–28 months depending on multiple-repair items.

Next steps: Staff will return with contract-execution documents and will monitor schedule and costs as construction is awarded and managed.