District reviews major high school, middle school and CTE plans as staff weigh site, schedule and temporary-relocation options
Summary
District staff updated the board on procurement and design milestones for the high school and middle school projects, recommended building a new CTE facility on a different pad to avoid chronic flooding, and outlined RFQ/RFP timelines for a construction manager; staff said soil borings will begin the week of May 18 and the district aims to open new facilities in fall 2028.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Dwayne Cash (project presenter) walked the board through schedule milestones and site options for the district's capital projects, including the high school, middle school and career and technical education (CTE) facilities.
Schedule and procurement: staff said the RFQ for the construction manager (CMR) was issued on May 8 with responses due May 29. Shortlisting was expected June 3, RFP issuance to shortlisted firms two weeks later, interviews the week of June 22 and board approval around the June 29 meeting.
High school and flood mitigation: designers showed schematic floor plans and explained a persistent site-elevation problem at the existing welding/CTE buildings. Cash explained the team’s preferred approach is to relocate CTE programs to higher ground so the new CTE building will sit above the roundhouse grade and eliminate chronic flooding rather than rely on pumps. Options discussed included demolishing and rebuilding the existing shop shell or relocating shop programs into a new CTE building.
Temporary-relocation alternatives: staff said a previously considered rental (Woodside) for temporary shop space would require fire alarms, upgraded heating, electrical work and other costly upgrades; after pricing those changes staff concluded the rental path was likely not cost-effective. Instead, a revised plan to build a new CTE structure south of the PAC could shorten site work, require fewer moves and allow the district to complete the CTE facility more quickly. Cash said the team could design and build a pre-engineered metal building with a finished exterior and aim to complete that work so programs could move by the winter break.
Middle school program and amenities: schematic designs call for grade-specific corridors, a flex theater with retractable seating, two gyms (competition and auxiliary), and a repositioned kitchen and media center. Board members discussed whether the district should build one central district kitchen or retain multiple kitchens and asked staff to bring kitchen consultants to upcoming design meetings.
Timeline and risks: staff confirmed topographic surveys are complete and soil borings were scheduled the week of May 18 to inform structural needs. The team reiterated that material and fuel price volatility is a risk to budgets and that the construction manager will play a key role in price validation and sequencing. The target for opening new facilities is fall 2028, subject to procurement and bidding results.
Quotes: "We think we could build it in 6 months," Dwayne said of a scoped CTE building option that would reduce interim moves; he added the team prefers a solution that minimizes the number of times programs and equipment must be relocated.
Provenance: Topic introduced with schedule and procurement details (SEG 939) and discussed through detailed site, program and timeline discussion (SEG 2170).