Committee hears $800,000 estimate from ODOT consultant for Dussell raised-crosswalk work
Summary
Officials said ODOT and consultant Gail produced a stage-two estimate of just over $800,000 for raised crosswalks on Dussell. The city seeks to avoid upfront costs and requested revisions to plans to reduce scope and cost; staff will return with markup and a revised estimate.
Get email alerts on the Pedestrian Infrastructure topic
No spam. Unsubscribe anytime.
Committee members heard that ODOT and consultant Gail provided a stage-two estimate for raised-crosswalk improvements on Dussell of just over $800,000 and discussed scope changes intended to reduce city exposure to additional costs.
A committee member said the consultant’s estimate used a conservative approach and warned that ODOT projects commonly incur change orders. City staff told the committee the goal is to avoid any upfront city spending; members requested adjustments to stage-two plans (including removing two raised crosswalk elements and realigning some crosswalks to be perpendicular to the road) to lower the estimate.
Staff said they will mark up the stage-two plans and ask the consultant to rework the estimate to reflect the reduced scope. The committee was told that if the project stays within the anticipated estimate, any costs above the project limit could become the city’s responsibility, so the city is pursuing a design that minimizes extras and possible change orders.
Next steps: staff will submit marked-up stage-two plans to ODOT/consultant Gail and return with a revised estimate and recommended scope adjustments for council consideration.