Board hears plan to expand Early Learning & Development Center, staff ask for $3.75 million and more square footage
Summary
District designers asked the board to revise the ELDC schematic and increase the project budget to $41.78 million (about $3.75 million more) to add three indoor gross-motor spaces, two sensory rooms and Jack-and-Jill bathrooms; staff said the changes respond to grant requirements and program needs and asked the board to bring the revision back for approval.
Get email alerts on the Early Childhood Infrastructure topic
No spam. Unsubscribe anytime.
Designers for DeKalb CUSD 428 told the school board that a revised schematic for the district's Early Learning & Development Center (ELDC) requires added footprint and money to meet early-childhood program needs.
At a board meeting April 1, Kyle, the ELDC schematic presenter, said the district's updated plan would increase the project budget to $41.78 million, an adjustment of roughly $3.75 million, and expand the building to about 60,000 square feet to add three indoor gross-motor spaces, two dedicated sensory rooms and Jack-and-Jill restrooms paired between classrooms. "We're trying to design an early childhood center, not an elementary school," Kyle said, explaining that smaller, specialized gross-motor areas reduce safety risks and let younger children use bikes, climbers and other equipment required by the program.
Why it matters: Staff said the changes reflect what architects and program leads learned during site visits and grant requirements for Preschool For All (PFA). The new gross-motor configuration would use three roughly 1,700-square-foot spaces so that groups of about 40 children operate safely rather than crowding a single large gym. Presenters said two sensory rooms are needed to provide a staffed calming space separate from OT/PT therapy areas.
Funding and timing: Staff described a funding approach that relies on district fund balance and e-zone (Meta) tax receipts the district has been tracking; they said the district currently monitors about $26 million in e-zone receipts and expects roughly $17 million more by November 2026. Presenters agreed to provide more precise fund-balance projections when the item returns to the board. Board members asked whether the proposed change affects the previously approved classroom count; designers said the revised footprint and programmatic rooms alter how the district should count "classrooms" (a 20-room configuration yields larger classrooms than 24 smaller rooms) and that a resolution amendment may be needed.
Questions and next steps: Trustees pressed staff for details on long-term operating costs, enrollment projections, and how additional staff and meals (the team suggested a service kitchen for delivered food) would be funded if the district pursues full-day expansion. Staff said the ELDC is projected to roughly double current early-childhood enrollment to about 600'650 students and that a Preschool For All expansion grant could support full-day options.
Board action: The board gave consensus to bring the ELDC schematic and funding adjustment back for formal consideration after staff supplies more-detailed fiscal projections. The presenters repeatedly asked for the additional square footage on the basis of instructional design and child safety.
What remains unclear: The schematic documents used slightly different square-footage figures (60,055 vs. 59,055 in discussion); staff committed to provide reconciled numbers and a clear fund-balance impact before any approval. The board also signaled that the previously authorized room-count language may need amendment if those nontraditional instructional spaces are counted as classrooms.