Rome board rejects 2026 resurfacing bids, directs a reduced rebid to cut about $300,000

Rome Board of Investment and Contract · May 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After bids for the 2026 cold milling and resurfacing project came in over budget, a city staff member told the board the bids will be rejected and the scope reduced by roughly $300,000; the board approved rejection and authorized a revised rebid.

The Rome Board of Investment and Contract voted May 14 to reject all bids for the 2026 cold milling and resurfacing project (RFB-2026-005) after city staff reported the proposals exceeded the available budget.

A staff member told the board, “The bids were opened above budget, and we weren't able to reach that funding level for this project,” and recommended rejecting the bids so the city could present a revised scope. He said engineers and the Department of Public Works would shift some work in-house and reduce some asphalt and extras "so we're looking to reduce the package by about $300,000 on our estimate." He added, “So it won't compromise the job.”

Following that recommendation, the board carried a motion rejecting the original bids. The clerk then read a subsequent resolution authorizing the city clerk to advertise for bids on a revised 2026 cold milling and resurfacing project (RFB-2026-005R); that motion also passed by voice vote.

The board did not record a roll-call tally in the record; actions were taken by voice vote. The staff explanation indicates the city plans to reduce contracted line items and rely on more in-house work from DPW and the engineering department to lower costs. No contractor names, new bid deadlines or an updated total project budget were specified in the meeting record.

Next steps: staff will prepare the reduced scope and the revised bid package for the board; the meeting record shows only that a revised RFB (2026-005R) was authorized for advertisement.