Rockport‑Fulton ISD bond high‑school project near substantial completion in June 2026, contractor says
Summary
Teal Construction/Claycomb told the Rockport‑Fulton ISD board that project billing is about 97% complete, $37.98M authorized of a $39.24M budget, and substantial completion is targeted for June 2026; punch‑list work will continue into July before full move‑in.
Get email alerts on the Bond Construction topic
No spam. Unsubscribe anytime.
Teal Construction and Claycomb project representatives reported to the Rockport‑Fulton ISD board that the high‑school component of Bond 02/2322 is approaching substantial completion, with project billing at roughly 97% and $37,980,000 authorized of the $39.24 million contract total.
The contractor representative said substantial completion is expected in June 2026 but noted that punch‑list and finish work — especially in an area identified as “Area G” (a new vestibule adjacent to the old band hall) — will continue through the summer. District staff and the contractor described an active punch‑list process (contractor, architect and district each maintain punch lists) and said crews will focus on interior finishes, storefront frames, roof drains and paving once students leave for the summer.
Board members asked about temporary certificates of occupancy for athletic areas and a timetable for final, full occupancy. Project staff said a temporary CO for athletics has been called in and that final completion is likely to extend into July because remaining punch‑list items require access while crews finish small, targeted work.
Fulton Elementary closeout activity was also discussed; staff said they will perform punch‑walks after students leave, replace a handful of identified floor tiles and finalize warranty and operations manuals before turning over remaining documentation to the district.