Paradise Canyon modernization on schedule; board delegates contract authority for library and phase‑five bids

La Cañada Unified School District Governing Board · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District reported on a five‑year modernization at Paradise Canyon Elementary, with prefab classrooms and seismic upgrades; trustees approved delegating authority to staff to accept contractor bids for the library relocation and phase‑five work to avoid construction delays.

District staff updated the board on the Paradise Canyon Elementary modernization: 20 new classrooms opened this year; the next milestones include TK/prek/K classrooms targeted for August 2026, summer work on the administration building/cafeteria/MPR, and four prefab buildings for the fifth‑ and sixth‑grade wings to be completed by August 2028 with final playground restoration in fall 2028.

Project manager Wendy Sinet emphasized seismic upgrades performed during modernization and the decision to use prefabricated offsite construction to reduce on‑campus disruption. She said trenching and supply-chain issues had been navigated and that the project remains on schedule and on budget.

Because the library relocation is a rapid‑turnaround summer contract and the phase‑five package’s bid schedule runs close to the board calendar, staff requested and the board approved delegating authority to district administrators to accept the lowest responsive bidders so work can begin immediately; the awards will be presented to the board for ratification at the next meeting.

Trustees also asked staff to prioritize visible site readiness for first‑day photos and confirmed contingency plans if bond funding timelines change. The board voted to approve the delegations and to proceed with the schedule.