Board approves easements, sidewalk repair orders and Old Plank Road intergovernmental agreement

Board of Public Works, City of De Pere · May 11, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The De Pere Board approved a WPS easement for temporary power at 925 South 6th Street, authorized pursuit of a storm-sewer easement related to the MSC project, approved 2026 sidewalk repair orders (166 properties) and 2027 gap-sidewalk orders for vacant parcels, and authorized an intergovernmental agreement with the town of Ledge View for Old Plank Road resurfacing.

The De Pere Board of Public Works approved a series of infrastructure and pavement-related motions at its May 11 meeting, enabling several near-term construction and maintenance activities.

WPS easement for temporary power: To provide temporary power for the Municipal Service Center remodel, the board granted approval for a 12-foot-wide trench easement for utility work at 925 South 6th Street so WPS can trench and install a temporary transformer feed.

Storm-sewer easement: As part of the MSC project staff asked the board to authorize pursuing an easement to relocate and upsize storm sewer lines in front of the MSC; the board authorized staff to proceed with obtaining the easement from the affected property owner to enable the planned sewer tie-in.

Sidewalk repair orders (2026): Engineering reported 166 repair orders from the annual one-eighth inspection program. Property owners have until the end of June to complete repairs themselves or request extensions; charges over $1,000 remain eligible for a five-year payback option. The board approved the 2026 orders and special charges.

Gap sidewalk orders (2027): Staff presented the parcels identified under the city’s gap-sidewalk policy and the board ordered sidewalk installation on listed vacant/frontage parcels for 2027, with the same payback provisions.

Intergovernmental Old Plank Road agreement: Staff described a cost-share arrangement with the town of Ledge View to pulverize and resurface Old Plank Road; the board approved the intergovernmental agreement and staff will forward it to council.