Board approves elementary abatement and greenlights middle-school renovation after debate
Summary
After presentations on asbestos abatement at BU View Elementary and construction issues at the middle school, the board approved $37,000 abatement and classroom carpeting at BU View and later voted 4–2 to proceed with a full middle-school renovation (carpeting, HVAC change orders and related work).
Get email alerts on the Facilities Renovation topic
No spam. Unsubscribe anytime.
The board approved two facilities actions after extended presentations and debate. Administration presented three related facility topics and cost estimates: asbestos abatement and replacement flooring at BU View Elementary; change orders and duct/utility adjustments at the middle school HVAC project; and a larger middle-school flooring/abatement/carpet ad-alternate that included hallways and classrooms.
BU View Elementary: Administration described exterior painting concepts and showed renderings, and presented a nearly $37,000 estimate to abate asbestos tile beneath existing carpet. For classroom flooring the administration recommended carpet tile for hallways and classrooms (one budgetary carpet estimate cited roughly $19,000 for carpet-tile work in a specific write-up and a $30,000 comparison for polished concrete). The board approved a motion to proceed with the abatement and classroom carpet tile work and asked staff to return with firm quotes for exterior paint and a proposed stage.
Middle school HVAC change orders: Project managers explained that some rooftop and site units had to be relocated to preserve windows and sightlines and that additional electrical routing (about 200 feet) and ductwork adjustments were required. A presented change order of $42,610 (plus related items) addresses power routing and unit siting; administration reported the overall HBAC/HVAC project still projects to finish below the original $5.88 million bid (estimated final cost ~ $5.2M with contingencies held).
Middle-school carpeting debate and final vote: The meeting then shifted into a lengthy debate over whether to carpet only classrooms or also include hallways. Arguments in favor of carpeting hallways cited sound reduction, safety and long-term uniformity; opponents raised concerns about stain/maintenance, vacuuming costs and whether the additional outlay was the best use of maintenance funds. Administrators warned scheduling and procurement timelines were tight and that delaying all work could raise costs. After discussion, the board voted 4–2 in favor of proceeding with the full middle-school project — classrooms, hallways and approved change orders — so contractors could schedule and complete the work this summer.
What the votes did and did not do: The board approved the BU View abatement and classroom carpeting (motion to proceed) and approved the HVAC-related change order for the middle school. The final middle-school package (carpet, abatement and ancillary work) was approved 4–2 to proceed; staff will return with finalized quotes for exterior paint and stage work at BU View.
Why it matters: The decisions advance multi-year maintenance and modernization work and use House Bill 292 maintenance funding and the board’s capital project contingency. The work is scheduled tightly to fit summer construction windows and to coordinate relocation of portable classrooms to the Pearson property.
What’s next: Administration will return with firm vendor quotes on paint and stage at BU View, finalize contracts/change orders for the HVAC work, and coordinate summer logistics to meet the targeted completion dates.