Liberty Elementary construction progressing; T Highway lane reductions planned during spring break

Waynesville R-VI School Board · February 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction manager reported Liberty Elementary remains on budget and on schedule for substantial completion in March 2027, with T Highway lane reductions planned the week of spring break (March 16–22) and intermittent daytime single-lane closures through April 3 to allow widening and turning-lane work.

Mr. Harrison updated the board on active construction projects, focusing on Liberty Elementary and the administration building renovation.

On Liberty Elementary, Harrison showed progress photos and said decking and steel for the commons areas are in place, concrete pours for classroom wings are underway, guardrail components are being installed and underground mechanical, electrical and plumbing work continues. He told the board the project remains "on budget and on schedule" with a target for substantial completion in March 2027.

Harrison also described traffic impacts tied to T Highway improvements adjacent to the Liberty campus: grading work is underway, and the district and contractor plan to reduce traffic to a single lane the week of spring break (March 16–22) to minimize school traffic conflicts. Intermittent single-lane daytime closures will continue March 23–April 3 with both lanes reopening for evening travel; access from Oakridge Drive to T Highway will be closed during this window with alternate access via Long Drive. Harrison said crews will avoid peak travel times when possible.

The administration building renovation is proceeding in phases. Harrison outlined a phased completion schedule: phase one (conference/training space) targeted for July 2026, phase two for November 2026 and phase three/substantial completion for May 2027; he said the project remains on budget though some phasing adjustments were needed.

Why it matters: Construction and nearby road work affect families’ travel routes and school access. The board was given specific dates and neighborhood access changes so families can plan around closures.

What’s next: Harrison asked the community for patience during lane reductions and said the district will continue to coordinate signage and school-zone flashing signals during construction.