Council backs design work for Dorchester Community Center’s Phase 1 after feasibility study
Summary
La Plata council authorized staff to advance architectural design for Phase 1 of the proposed Dorchester Community Center — a roughly 7,600-square-foot gym/multipurpose building — and to issue an operator RFP after consultants confirmed site feasibility and staff identified $1.25 million in state grants, leaving a funding gap to be analyzed.
Get email alerts on the Dorchester Community Center topic
No spam. Unsubscribe anytime.
Mayor Janini James and the Town Council voted May 12 to direct staff to proceed with design and preliminary site preparation for Phase 1 of the Dorchester Community Center at 402 Potomac St.
Town Manager Chuck Stevens and consultants from Cao Barrett and Patuxent Architects told the council a feasibility study shows the approximately 2.1-acre development site can accommodate a phased community center. Consultants described a three-phase approach: Phase 1 (about 7,600 square feet) would deliver a gymnasium/multipurpose assembly; Phase 2 (about 1,900 square feet) would provide entry control and lounge space; and Phase 3 (roughly 7,500 square feet) would add community support spaces and potential daycare.
Consultants said the property is currently zoned Industrial High (IH), which does not allow a community center by right; rezoning to a Central Business (CB) or a discretionary land-use approval will be required. They reported the site benefits from existing public water and sewer and is technically suitable for demolition and new construction. "There is a high level of success for this project from a technical feasibility standpoint," consultant Anthony M. Alexander said during the presentation.
On costs, staff and consultants offered planning-level estimates, including a soft-cost allowance of about 20–25 percent for design, engineering and permitting. The rough order-of-magnitude budget presented: Phase 1 approximately $3.12 million; Phase 2 approximately $870,000; Phase 3 approximately $2.17 million; full single-story buildout about $6.1 million. Consultants recommended advancing design promptly to protect a time-limited state grant opportunity.
Stevens told council the town has secured about $1.25 million in state grant funding (plus a $100,000 ARPA allocation noted in staff materials) that could be applied to Phase 1, and warned the earliest grant(s) include expiration timelines. "One of the critical deadlines is a grant that is scheduled to expire in June of next year," he said. Staff will prepare a funding-gap analysis, pursue additional grant opportunities and return to council with financial projections before committing to construction contracts.
Council members supported moving Phase 1 forward while reserving judgment on Phases 2 and 3 until funding is identified. Several members asked that the Phase 1 design be viable as a stand-alone, operational facility. Consultants said the build can operate while later phases are added and that combining phases can yield economies of scale, but that Phase 1 has been designed to function independently.
Council also asked staff to issue a formal RFP for facility operations, targeting nonprofit or community-based operators. Stevens said responses to an earlier notice-of-intent showed a healthy applicant pool that includes youth-mentoring organizations, workforce/technology education providers and social-service partners with local ties.
The council’s authorization directs staff to advance design and engineering services for Phase 1, initiate an operator procurement process, and return with a funding-gap analysis and an integrated timeline before any construction contract is executed.