Hemphill County receives airport and construction reports; pavilion and museum projects complete
Summary
Airport Manager Bill Kendall briefed the court on AWOS replacement, IIJA funding and other airport projects; Southwest Architects reported that pavilion and museum construction work was completed and paid for from county reserves.
Get email alerts on the Infrastructure Projects topic
No spam. Unsubscribe anytime.
The Hemphill County Commissioners' Court received project updates from county staff and outside architects at its March 30 meeting, including airport infrastructure work and the completion of pavilion and museum construction.
Airport Manager Bill Kendall updated the court on planned and ongoing airport work. Kendall reported on replacement of the Airport Weather Observation System (AWOS), referenced potential IIJA (Infrastructure Investment and Jobs Act) funding, and discussed airport beacon replacement and a water gap replacement project. The transcript records those topics as informational updates; no formal action or funding vote on these projects was recorded at this meeting.
Jeff Heffelfinger of Southwest Architects presented construction reports for two county projects. On the pavilion, Heffelfinger said all work had been completed; Judge Johnson noted the pavilion was being paid for from county reserve funds and that the county had approved the project. Heffelfinger also reported that museum construction work was complete. The transcript contains no further budgetary detail or contractor change orders for these projects.