Officials outline timelines for SR21 widening and Effingham Parkway phases
Summary
At the May 20 committee meeting in Springfield, GDOT and county staff reviewed bridge replacements, roundabout schedules, corridor widening plans and resurfacing contracts; staff were asked to verify right‑of‑way timeframes and phased completion dates for Effingham Parkway.
Get email alerts on the Transportation Projects topic
No spam. Unsubscribe anytime.
Springfield, May 20, 2025 — Officials reviewed a slate of state and county road projects and assigned follow‑up tasks after the Effingham County area transportation committee received a Georgia Department of Transportation (GDOT) update and staff summaries.
Katie Proctor of the Georgia Department of Transportation reviewed preconstruction and active projects, including a bridge replacement at SR119/Old River Road (Ogeechee River) with a scheduled July let date, a planned roundabout at SR17 at Marlow Road/Sandhill with a Preliminary Field Plan Review expected in October, and a bridge replacement on I‑95 at the Savannah River with a July letting. Proctor also listed a PFPR by year‑end for a roundabout at SR26/US80 at CR311/Sandhill.
County Manager Tim Callanan told the committee that Effingham Parkway is 83 percent complete and said his understanding was that the project now has phased completion targets: Phase 1 (Gateway Parkway to 30) in April 2026 and Phase 2 (Gateway Parkway to Blue Jay) in July 2026. Committee members asked Proctor to verify the phased completion dates and to provide a timeframe for right‑of‑way (ROW) acquisitions for the SR21 widening work.
Staff described project details across several corridors: full reconstruction and paving of Low Ground Road between McCall and Midland with 11‑ft lanes and paved shoulders; multi‑phase improvements on Blue Jay Road including resurfacing to Hwy 21 and widened segments with roundabouts; Goshen Road widening to three lanes with drainage upgrades (ROW acquisition in progress); and Old Augusta Road work planned in two phases, the first of which (SR21 to Logistics Parkway) is slated for bid in January 2027. A corridor study for SR80 and Old River Road focused on four‑laning to SR280 was also reported.
On funding and maintenance, staff said District 3 resurfacing was awarded to Reeves and District 3–5 work to McLendon with fall completion targeted for some contracts; they noted chip seal work is limited to warm weather windows. The committee discussed whether the SR21 widening and the SR30/Hodgeville roundabout should be included in the Transportation Improvement Program (TIP).
Members flagged public engagement steps: several suggested holding town halls on Goshen Road and SR21 once designs are complete and coordinating dates with municipalities; staff were also urged to communicate which projects were completed with TSPLOST funds.
Action items recorded at the meeting direct Katie Proctor to (1) provide a timeframe for ROW acquisitions related to the SR21 widening and (2) verify the Effingham Parkway phased completion dates; Wykoda Wang and Proctor were asked to follow up after the meeting. No votes were taken on project funding or TIP inclusion at this session.
The committee will await Proctor’s follow‑up on ROW timeframes and schedule verification before taking further formal steps on TIP inclusion or project sequencing.