County staff outline $12–$15 million Bowers Field capital project bundle; FAA could cover most costs
Summary
Kittitas County public works staff told commissioners the FAA is recommending bundling several Bowers Field projects into a single larger project estimated at $12–$15 million; FAA funding typically covers 90% with the county responsible for about 10%, potentially reduced to roughly 5% with state aviation grants; timing is planned for 2028–2029 and no action was taken.
Get email alerts on the Bowers Field topic
No spam. Unsubscribe anytime.
Joshua Fredrickson briefed the Board of County Commissioners on the Bowers Field Capital Project Plan. He said the Federal Aviation Administration is indicating that several previously phased projects — hangar taxi lane expansion, a parallel taxiway, runway lighting improvements, and runway narrowing — should be bundled into one larger project estimated at $12 million to $15 million.
Fredrickson told the board that airport projects are typically funded at 90% by the FAA with the county responsible for approximately 10% and that Washington State aviation grant funding may offset half of the county share, leaving an estimated county obligation of about 5% if state funds are secured. He said timing for the project is currently anticipated in the 2028–2029 timeframe and that no action was taken at the study session.
The briefing was informational; staff indicated planning and budget forecasting will be necessary to prepare for the county match if the FAA pursues bundled project funding.