Board approves not-to-exceed $750,000 authorization to upsize Mountain Ridge waterline; county utility to reimburse $150,000

Berkeley County Schools Board of Education · May 19, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

To avoid schedule delays on Mountain Ridge Primary, the board approved a not-to-exceed $750,000 change order to upsize a waterline from 12" to 16" and to proceed with ordering long-lead materials for fire suppression; the Berkeley County Public Water Authority agreed to reimburse $150,000 toward the upgrade.

The Berkeley County Schools Board authorized a not-to-exceed change order of $750,000 to upsize a waterline and progress related fire-suppression work at Mountain Ridge Primary, a measure board members approved May 18 to keep construction on schedule.

Project staff and the superintendent told the board the Mountain Ridge site initially called for a 12-inch water main, but the local water authority requested a 16-inch line. The Berkeley County Public Water Authority has agreed to reimburse $150,000 toward the extra pipe cost. Project managers described long lead times for a fire-suppression storage tank and emphasized urgency: approving the not-to-exceed change order will allow material orders to proceed while the project team continues to negotiate final contractor labor pricing.

Staff described the logistics to board members: upsizing the line affects trenching depth and width and requires coordination of fire hydrant placement. The change-order package was presented as a time-sensitive measure intended to prevent the loss of the critical August opening target by buying the long-lead items immediately and resolving final pricing later with the contractor.

Board members asked for clarification on what the change order covers and how costs are being apportioned; staff said the water authority will cover $150,000 and the district will pursue the remainder within the contract’s contingency and coordination with McKinley Architecture and the contractor. The board voted to approve the authorization to proceed under a not-to-exceed amount to avoid schedule slippage.

Next steps: staff will continue negotiations with the contractor on final labor/price details, finalize itemized costs for the board and report back with a final tally once negotiations conclude.