Commissioners approve $1.43 million courthouse roof restoration, staff corrects typo mid‑presentation
Summary
Douglas County approved a $1,428,507 contract with Escola Roofing & Waterproofing for courthouse roof restoration after staff corrected a typographical contract amount during the meeting; the project follows a July 2025 nuclear scan that identified weakened roof areas and includes a 20‑year warranty from the manufacturer.
Get email alerts on the Facilities Contracts topic
No spam. Unsubscribe anytime.
The Douglas County Board of Commissioners approved a contract on May 18 to restore the courthouse roof after staff described structural weaknesses identified in a July 2025 nuclear scan.
Director Morgan presented the recommended award to Escola Roofing & Waterproofing under the Omnia Partners contract for a corrected contract amount of $1,428,507 (staff noted a typographical error on the agenda that listed $1,444,507). Morgan said identified weak areas include the rotunda and lower roof levels, with visible interior ceiling damage in the cupola area. The presenter described the scope as a roof restoration focused on removing and repairing damaged areas and applying manufacturer products rather than a full roof replacement in all areas.
A representative with Tremco (Cameron Holbrook) said the project would take about 8–12 weeks to complete, weather dependent, and include warranty coverage. Commissioners asked whether the contract included renewals or ongoing fees; staff and the vendor said there is no renewal and the manufacturer’s warranty covers leaks or damage for 20 years. County legal review was flagged as pending; commissioners requested warranty and scope language be verified in contract exhibits prior to signature.
The board unanimously approved the contract and authorized the chairman to sign all related documents pending final legal review. Staff said work would likely begin after contract ratification in July 2026 with roughly 3 weeks for mobilization followed by the 8–12 week construction window.
Quote: "So 1 correction I do have though is, I had put on there $1,444,507. It's actually was a typo... It's $1,428,507," Director Morgan said during the presentation.
Next steps: legal will confirm warranty and scope language; facilities staff will coordinate mobilization and provide a schedule to the board.