Board approves $337,077 in owner‑requested change orders for Southern Middle School renovations
Summary
Trustees approved two large owner‑requested change orders for Southern Middle School — $214,939 to extend tile throughout corridors and $122,138 to replace library furniture — funded from contingency and budgeted amounts.
Get email alerts on the Construction Change Orders topic
No spam. Unsubscribe anytime.
The Wilson School Board voted to approve owner‑requested change orders for Southern Middle School that together total $337,077.
Superintendent Dr. Trickett told the board the change orders were requested by the owner (the Wilson School District) after reviewing bid packages and available contingency funds. Change Order 2 ($214,939) covers extending tile throughout corridor areas rather than painting (the figure includes the painting credit), and Change Order 3 ($122,138) covers full replacement of library furniture and shelving to match the standards set at West Middle School.
Trickett said the costs were budgeted and would be paid to the general contractor, ECI Construction, which coordinates subcontractors and procurement. He described the intent as bringing Southern to a comparable standard with other district middle schools and said the work is already included in the project contingency in the capital budget.
Board members asked whether the items would change the overall budget; Trickett said the work is already budgeted and the change orders alter the amount paid to ECI Construction but not the appropriation from district contingency. Trustees approved operations items 10.1–10.5, including the Southern change orders, by roll call (8–0).
The board did not table or amend the orders; work will proceed as part of the phased renovation schedule for Southern Middle School.