KDHE cancels early childhood IT contract after testing failures; roughly $3.2M paid
Summary
A monitoring memo presented to the committee shows KDHE terminated a vendor contract for the early childhood data integration project after repeated data-conversion and testing failures; KDHE paid nearly $3.2 million of a $5.5 million contract, mostly from ARPA funds, and legal options for recouping funds are under review.
Get email alerts on the IT Contracts topic
No spam. Unsubscribe anytime.
Legislative Post Audit staff told the committee that the Kansas Department of Health and Environment (KDHE) canceled its contractor for the early childhood data integration and system enhancement project after the project entered a red-alert status for schedule, cost and quality.
Katrin Osterhaus (post audit) summarized the monitoring memo: issues intensified in 2025, KDHE issued a cure letter to the contractor, and the Office of Procurement and Contracts terminated the contract effective May 13. "The project started having problems in 2025," Osterhaus said, and the memo shows problems with transparency, poor quality, and lack of consistent technical assistance between KDHE and the vendor.
Financials: the monitoring summary reported KDHE paid nearly $3,200,000 toward a $5,500,000 contract. That breakdown included about $2,800,000 for originally planned deliverables, roughly $220,000 for approved change requests that were finished, and $120,000 in quarterly monitoring fees to the Kansas Information Technology Office. Most expenditures were funded from an ARPA grant; roughly $340,000 came from the State General Fund.
KDHE response and technical issues: Secretary Janet Stanek told the committee the contract structure limited clawback opportunities but legal counsel is exploring options to recover funds. Stanek said the vendor delivered some individual components but that collective testing—user acceptance testing (UAT)—revealed data conversion and integration failures that made the system untrustworthy. KDHE CIO Bob Jones said data conversion from a 20-year-old system caused persistent defects during UAT and that the vendor had not completed conversions to KDHE's expectations.
Committee concerns and procurement follow-up: legislators pressed KDHE on whether the vendor misrepresented prior experience and whether a referral to the attorney general was warranted; KDHE said it is consulting legal counsel and procurement records will inform future decisions about the vendor. KDHE said it will reuse remaining funds to stabilize and enhance its existing system and has engaged consultants to upgrade the current application's infrastructure and software while the agency determines a longer-term approach.
Next steps: agency counsel is reviewing legal options, procurement records will note the vendor's performance for future procurement considerations, and KDHE is working to stabilize the current system while continuing oversight of remaining work.
The committee accepted the monitoring memo and asked agency staff for additional details about any clawback or legal actions.