Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Lemont staff: 30 lead service lines replaced in phase 1; phase 2 slated for summer

Lemont Village Board · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Village staff reported on Feb. 9 that 30 lead service lines have been replaced in phase 1 of Lemont’s program and that phase 2 (26 replacements) will begin this summer; contractor IAC is performing the work and residents reported minimal problems to date.

Village staff gave a progress update on Lemont’s lead service-line replacement program at the Feb. 9 meeting, reporting that 30 private lead service lines were replaced in phase 1 and that restoration of affected properties will begin in spring.

Staff said phase 2 is scheduled to begin in summer and will replace about 26 additional lead lines; phase 3 is still in inventory and planning. The village confirmed the work is being done under contract with IAC, that lawn restoration and other property restoration work will be handled by the contractor, and that residents have reported few problems to date.

A resident who had work performed said the contractor showed up on time, minimized yard disturbance and completed work faster than expected; staff said the program is proceeding smoothly and will continue in coming months.