Granite County approved HDR Engineering’s pre-inspection report and cover letter for the Flint Creek FERC inspection and set Georgetown Lake outflow at 20 cubic feet per second for a week; county and dam tender discussed lake level (reported 6 inches below full pool) and spillway use.
Get email alerts on the Flint Creek Dam topic
No spam. Unsubscribe anytime.
County officials approved submission of a pre-inspection preparation report and cover letter to the Federal Energy Regulatory Commission (FERC) for the Flint Creek Dam project and set a temporary outflow for Georgetown Lake during the April 7 meeting.
Jessica Rudd of HDR Engineering said the pre-inspection package was complete with only minor administrative updates and that it must be submitted 30 days before the scheduled inspection. The commission approved the report and cover letter so HDR can file it on schedule; the discussion included a notation that a valve vault at the site may qualify as a permit-required confined space and will require follow-up to confirm regulatory obligations.
Separately, based on the USGS lake gauge and the dam tender’s weekly report that listed the lake level at 6 inches below full pool (6429.00 feet), Commissioner Adler moved to set the Georgetown Lake outflow to 20 cubic feet per second (CFS) for one week; Commissioner McLure seconded and the motion passed unanimously. Public commenter Spencer Parke urged filling the lake fully and then dumping it out; county officials and the dam tender said the spillway should be used only for emergencies.