Commission approves 106 Bridge Street application with conditions, highlights live oak protection and setback issues
Summary
A proposed new house and carriage house at 106 Bridge Street was the meeting's most contested item: commissioners approved determinations and later approved the application with conditions, while directing the applicant to resubmit drawings to HPRC and provide UDO administrator confirmation regarding setback relief tied to preserving a large live oak.
Get email alerts on the 106 Bridge Street topic
No spam. Unsubscribe anytime.
The commission spent the longest portion of its meeting on a large new-home and carriage-house proposal at 106 Bridge Street, approving determinations but imposing conditions that prioritize protecting a large live oak and clarifying setbacks along an unopened right-of-way.
Planning staff described the constrained site — directly across from Oyster Factory Park and including an "unopened right away" (a so-called ghost road) — and flagged a number of concerns: the carriage house as drawn was slightly taller than the main house (contrary to UDO expectations that carriage houses be secondary), the roofline was complex, and two trees were proposed for removal. Staff recommended determinations and a set of conditions including providing a tree-removal permit application, chimney cap and railing details, and confirmation that at least 75% tree canopy coverage at maturity would be maintained.
Architect Ansley Manuel and homeowner representatives answered questions and explained site constraints created by an 84-inch-diameter live oak the team sought to preserve. Commissioners repeatedly urged shifting the main house and carriage house where possible, relocating a storage/service yard and refining the carriage-house roofline to reduce scale. "That tree is super important," one commissioner said in urging a design that preserves the canopy.
After votes to approve the required determinations, the commission approved the application with staff recommendations, added a requirement to show bridge footings details, and required that redesigned plans be brought to HPRC for final discretionary review of setbacks and tree impacts. The commission and staff emphasized close coordination with the UDO administrator about any minor setback relief that may be granted to preserve the oak.
The applicant agreed to work with staff on revised drawings and to seek any necessary administrative relief; the commission noted a typical turnaround to have revisions ready for a subsequent monthly meeting.